Place planned maintenance into the weekly schedule before allocating production. Identify which machine is unavailable, for how long and which compatible loads can move elsewhere. Confirm parts and service attendance in advance. Include restart checks and any required trial load; the end of the technician's visit is not always the same as the machine's return to normal output.
Put maintenance blocks into the schedule before accepting delivery commitments. The remaining capacity is the available production resource; nominal machine hours that are deliberately unavailable should not be counted twice.